East Vancouver
12 Months
$197,500
Client's goals
The homeowners wanted to maximize the functionality and value of their home by converting their unfinished basement into a legal two-bedroom suite.
Converting the basement into a legal 2-bedroom, 1-bathroom suite
A new kitchen and bathroom for the suite
A separate, private entry
Retaining one basement room for the homeowners
Adding a powder room to the upstairs ensuite
A new upstairs laundry area
Overview
Roka Projects converted the unfinished basement of an East Vancouver home into a legal two-bedroom suite with its own kitchen, bathroom, and private entry, while keeping one basement room for the homeowners' own use. Getting there took more than finishing work: the sewer line was re-graded all the way to the city connection to drain the new plumbing, the mechanical room was reconfigured into a properly separated space, and drywall containing asbestos was removed by a certified hazmat contractor. Upstairs, the project added a powder room to the ensuite, a new laundry area, and a rebuilt second-floor patio.
Scope of work
Unfinished basement converted into a legal two-bedroom, one-bathroom suite
New suite kitchen and full bathroom
Separate, private suite entry
One basement room retained for the homeowners' own use
Sewer line re-graded to the city connection for reliable basement drainage
Mechanical room reconfigured into a properly separated space
Certified asbestos abatement with selective demolition
Powder room added to the upstairs ensuite
New upstairs laundry area
Second-floor patio rebuilt to modern code
Challenges & Solutions
Sewer Line Drainage
Challenge: Sewer Line: the existing sewer connection inside the house was not low enough to allow proper drainage for the planned new bathroom and kitchen.
Solution: We re-graded the sewer line all the way to the city connection, lowering it enough to ensure reliable drainage and full functionality of the new fixtures.
Mechanical Room Separation
Challenge: Mechanical Room: the home's existing mechanical room was located within the area planned for a future basement suite, limiting the ability to create a properly separated unit.
Solution: We reconfigured the layout to establish a properly separated mechanical space.
Asbestos in the Drywall
Challenge: Asbestos: testing revealed that the drywall throughout the home contained asbestos, posing both health risks and demolition cost challenges.
Solution: We brought in a certified hazmat contractor to perform selective demolition, removing only the necessary drywall.
A Rotten Second-Floor Patio
Challenge: Patio: the home's second-floor patio was completely rotten and structurally unsafe.
Solution: We rebuilt the patio from the ground up, bringing it up to modern code standards.
Result
What was an unfinished basement is now a legal, self-contained two-bedroom suite with its own kitchen, bathroom, and private entry, and the homeowners kept a room of their own on the same level. Today the suite runs as an Airbnb rental: the owners use it when they need it and rent it when they want to. The house above got its share of the upgrade too, with a new ensuite powder room, a proper laundry area, and a rebuilt patio. Behind it all sits the work that makes a suite truly legal: re-graded drainage, separated mechanical, and certified asbestos removal.
BEFORE photos
Similar Projects
We completed a nine-month full interior renovation of a newly purchased Downtown Vancouver townhouse.
After a basement flood, the homeowners needed the underlying water problems solved and the home protected for the long term.
We rebuilt the structure beneath a suite entry in East Vancouver over two weeks in March, as part of the owner's suite legalization.
We replaced the aged rubberized driveway of a North Vancouver home near Edgemont Village with a new concrete driveway.
We rebuilt a deck over the garage of a Burnaby home after the original had failed.
We rebuilt the carport entry level of a Lynn Valley split-level home in North Vancouver for repeat clients, adding a mudroom, a new laundry room and a guest suite.
It began as a fence that blew down in a storm and became a full exterior renovation when the fence turned out to be holding onto a rotting timber retaining wall, and the wall turned out to be holding up the neighbour's driveway.
More than a century old and renovated in stages by previous owners, this Cambie-area home had the character the family wanted to keep, but not the layout, structure or systems they wanted to live with for decades to come.
The owners wanted their galley kitchen to work better without major structural changes, with more light and a connection to the patio, and their main bathroom rebuilt around a walk-in shower.
A closed-off East Vancouver condo kitchen opened up by removing several walls, connecting kitchen, dining, and living into one bright space. When the walls came down, deteriorated copper piping came out too. Newer plumbing than the building now.
An unfinished East Vancouver basement, now a legal two-bedroom suite with its own kitchen, bathroom, and private entry. Re-graded drainage and certified asbestos removal made it truly legal. It runs as an Airbnb today.
A dated kids bathroom in Cloverdale, fully removed and replaced in six weeks. Durable, easy-care finishes that shrug off daily wear, plus the storage a busy family needs. Built to grow with the kids.
An East Vancouver home refreshed in one pass: a new kitchen with the laundry hidden in matching millwork, all 2.5 bathrooms redone to match, engineered wood across both levels. Two and a half months.
A North Vancouver home whose basement suite needed its own way in. Roka cut a new opening in the foundation and built the entry properly: concrete, drainage, stairs, and railings. Two months, and both households got their privacy back.
A leaning concrete retaining wall in Pitt Meadows, replaced with a simple wood wall in a single week. With redevelopment already planned, the owners needed a few more safe years, not a forty-year rebuild. The right call was the simplest one that worked.
A cracked support under this Vancouver carport and patio, repaired first. That work uncovered garage doors framed with no header at all, since reframed properly. New walkway and rebuilt stairs finished it in three weeks.
A buyer inspection flagged structural items on this Horseshoe Bay home. Roka priced the fixes so the deal could close, then completed them after possession. Deck rebuilt, staircase and gutters put right.
A Kitsilano condo refreshed front door to bedroom. A dated bathtub became a walk-in shower and new flooring runs throughout. The kitchen opened up with a new counter, all in six weeks.
An East Vancouver main floor opened up around a new island kitchen. A dividing wall came out and the structure below was reinforced to carry it. Reconfigured bathroom and a gas fireplace round it out.
A Delta main floor modernized around a new kitchen. A gas fireplace, feature wall, and new flooring throughout tie it together. Roof, attic, and chimney put right first.
A leaking West Vancouver patio, replaced with new concrete and a glass guardrail. A failing structural beam was reinforced underneath. Four months, solid from the ground up.
One Yorkwood Hills neighbour told the next. Roka converted a walk-in closet into a private ensuite, four units and counting. Each got its own layout and finishes.
A durable, kid-proof bathroom built to last. New doors, trim, paint, and carpet refreshed the whole upper floor. Six weeks, on budget.
A pool that would not hold water, even after another repair. New finish, fixed jets and light, rebuilt mechanical room. Every leak found and sealed.
A Commercial Drive condo made safer for aging in place. New kitchen finishes, an accessible bathroom, and vinyl tile throughout. Exposed Poly-B plumbing replaced too.
Window rot caught and repaired before it spread. New window and siding finished the wall right. Exterior stairs rebuilt for safety, in two weeks.
A century-old Kitsilano home's old bathtub, replaced with a custom walk-in shower. Asbestos abatement cleared the way first. One month, no surprises.
We renovated this condo bathroom just off Commercial Drive in six weeks: the bathtub came out and a custom walk-in shower took its place, joined by a new floating vanity, continuous tile running through the whole room, and a heated floor underfoot.
A False Creek condo refreshed top to bottom. New kitchen, two renovated bathrooms, and a fireplace-centred living room. Air conditioning added for the summer months.
A previous contractor cut into a structural shear wall, a real seismic risk. Roka restored it to engineered spec and rebuilt the bathroom right. One month, fully contained.